Construction of Data Centre, Masaka – Plot 20 Speke Road for Centenary Development Group Limited

  • Home
  • Portfolio
  • Construction of Data Centre, Masaka – Plot 20 Speke Road for Centenary Development Group Limited

Construction of Data Centre, Masaka – Plot 20 Speke Road for Centenary Development Group Limited

Nexus (U) Limited successfully undertook the construction of a Data Centre located at Plot 20 Speke Road, Masaka, for Centenary Development Group Limited. This project aimed to establish a state-of-the-art facility to support advanced data management, storage, and processing for the client’s operations.


Scope of Work
  1. Site Preparation and Civil Works:

    • Clearing and leveling of the site to prepare for the foundation and construction.
    • Excavation, foundation laying, and structural construction of the data centre building to meet technical specifications.
  2. Data Centre Infrastructure:

    • Design and construction of server rooms, control rooms, and auxiliary spaces such as offices and storage rooms.
    • Installation of raised flooring systems for proper cable management and airflow.
    • Construction of fire-rated walls and ceilings to ensure fire safety compliance.
  3. Electrical Systems Installation:

    • Installation of a high-capacity electrical system, including transformers, power distribution units (PDUs), and backup generators to ensure uninterrupted power supply.
    • Integration of energy-efficient lighting systems and emergency lighting.
  4. Cooling and HVAC Systems:

    • Deployment of advanced Heating, Ventilation, and Air Conditioning (HVAC) systems to maintain optimal temperatures and humidity levels for data centre operations.
    • Installation of precision cooling systems for critical equipment areas.
  5. IT Infrastructure Setup:

    • Structured cabling for data and power connections to support high-performance servers and networking equipment.
    • Space allocation for future equipment expansion while ensuring easy accessibility for maintenance.
  6. Security and Access Control:

    • Installation of biometric access control systems, surveillance cameras, and perimeter security measures to safeguard the facility.
    • Implementation of alarm systems and fire detection and suppression systems for comprehensive safety.
  7. Power Backup and Redundancy:

    • Integration of an Uninterruptible Power Supply (UPS) system and backup generators to guarantee operational continuity in case of power outages.
  8. Final Finishing and Testing:

    • Finishing works, including painting, flooring, and installation of signage.
    • Comprehensive testing and commissioning of all systems to ensure compliance with international standards.

Key Features and Benefits
  1. State-of-the-Art Infrastructure: The facility is equipped with modern systems to ensure high performance, reliability, and scalability.
  2. Uninterrupted Operations: Redundant power and cooling systems provide assurance against downtime.
  3. Enhanced Security: Advanced access control and surveillance systems safeguard sensitive data and equipment.
  4. Compliance with International Standards: The data centre was built to meet global standards for safety, efficiency, and performance.

Completion and Outcome

The Construction of the Data Centre at Masaka, Plot 20 Speke Road, was successfully delivered by Nexus (U) Limited for Centenary Development Group Limited. The facility now serves as a critical hub for data storage and processing, reinforcing the client’s capacity to manage its operations effectively. This project highlights Nexus (U) Limited’s expertise in delivering sophisticated, high-tech infrastructure solutions.

Shopping Cart (0 items)